Operations and projects

Sininda

  • Location
    Republic of Buryatia
  • Mining
    Underground mine
  • Deposits
    Nerundinskoye
  • Processing
    Gold processing plant
321 kg
gold production in 2024
7,543 kg
C1 + C2 gold reserves as at January 1, 2025

OPERATING RESULTS FOR 2022-2024

Production complex 2022 2023 2024
Run-of-mine material thousand m³ 67 89 104
Ore mined (in dry weight) thousand t. 116 135 180
Ore processed at gold processing plant thousand t. 88 137 195
Doré gold produced kg 175 229 321
Gold produced kg
174 227 321