Nizhne-Yakokitskiy

  • Location
    Republic of Sakha (Yakutia)
  • Mining
    Open-pit
  • Deposits
    Nizhne-Yakokitskoye ore field
  • Processing
    Heap leaching, separate ore processing facility
2,558 kg
gold production in 2024
35,337 kg
C1 + C2 gold reserves as at January 1, 2025

Mineral resources and ore reserves of the Nizhne-Yakokitskoye ore field deposits were audited in accordance with the guidelines of the JORC Code. The Probable reserves were estimated at 33,865 kg of gold; Indicated resources, at 34,596 kg of gold and Inferred, at 2,386 kg.


Operating results for 2022-2024

Production complex
2022 2023 2024
Run-of-mine material
thousand m³  15,903 12,693 14,702
Ore mined thousand (in dry weight) thousand t  6,824 3,922 3,177
Ore stockpiled thousand t  4,327 4,563 3,883
Doré gold produced  kg 3,256 3,111 2,551
Gold produced kg
3,261 3,142 2,558

Khvoyny strategic project

  • Location
    Khvoynoye deposit (Nizhne-Yakokitskoye ore field) in the Aldan district of the Republic of Sakha (Yakutia)
16.8 TONNES OF GOLD
Balance reserves С1+С2
2.5 TONNES OF GOLD
Expected production
3 mln TONNES OF ORE
Processing capacity
Project schedule
  • 2021 Start of the project
  • 2022 Positive reviews of design documentation were obtained from the Main Department of State Expertise and State Ecological Expertise Authority
    The most of machinery and equipment contracted
    General contractor for construction chosen
    Construction of infrastructure and utility systems (roads, water conduit, electrical substation and electricity lines) progressed
  • 2023 Construction of the main production complex: main building, filtration facility, auxiliary workshops
    Construction of infrastructure, including an electric substation and a boiler room
    Installation of the main elements of the plant production chain completed, that of wet semi-autogenous grinding mill and overflow ball mill
  • 2024 Main construction stage: equipment is fully supplied, installation is in progress
  • 2025 Construction stage completed